Halsey Road, Elizabeth East Footpath
The footpath on Halsey Road, Elizabeth East is being replaced part of Council’s annual footpath renewal program. We understand this may cause some minor disruption, and ask that residents please observe traffic and pedestrian safety signage whilst work are undertaken.
Start Date: 24 October 2022
Duration: 16 weeks, weather permitting
Washington Drive, Craigmore Footpath
Footpath renewal works on Washington Drive, Craigmore will re-commence as part of Council’s annual footpath renewal program. This work involves the renewal and widening of the existing footpath from 1.2m wide to 1.5m, as well as the upgrade of kerb ramps for accessibility compliance. We understand this may cause some minor disruption, and ask that residents please observe traffic and pedestrian safety signage whilst work are undertaken.
Traffic Management will be in place to ensure the safety of the public and our workers, please see the traffic management plan (here).
Forecast Start Date: 7 November 2022 – note the on-going wet weather may result in a delay to this start date
Duration: 16 weeks, weather permitting
Peachey Road and Curtis Road Intersection
The intersection of Peachey Road and Curtis Road is being upgraded as part of Council’s road safety upgrades program. We understand this may cause some minor disruption and ask that residents please observe traffic and pedestrian safety signage whilst work are undertaken.
Start Date: 14th November 2022
Duration: 6 weeks, weather permitting