The Sheedy Road Upgrade in Virginia commenced on 27 January, between Old Port Wakefield Road and O’Loughlin Road, to make travel easier for motorists, pedestrians and cyclists.
These works will lift the road to an urban standard, delivering a new smooth surface and upgraded infrastructure including footpaths, street lighting, kerbing and stormwater systems.
The project is expected to be completed in late winter 2026.
Experience during construction
Temporary disruption is expected during construction, with detours via Park Road and traffic management measures in place throughout the project to keep the community moving safely.
Your updates
Project update - 20 February 2026
- Around 80 metres of pipe has now been installed at Coratina Reserve, including completion of the basin drainage works within the reserve.
- From 02 March for approximately six weeks, Sheedy Road will be closed between Coratina Reserve and O’loughlin Road for the installation of a stormwater pipe underneath the road.
- Traffic will be detoured along Park Road. Local traffic access will be maintained. Detours will be clearly marked.